A week after the start of the production in Petrohemija, after two- month general overhaul, plants are working stable and with no greater problems.
According to Gavrilo Knjeginjić, Director of Ethylene plant, the plant is working following the operative plan and the capacity of processing 1,320 tons of raw materials per day has been reached.
In the High Density Polyethylene Plant all three sections- polymerization, finishing and packaging have started working. HDPE is working with its maximum capacity, of almost 10 tons per hour, and the first goods have already been ready to be delivered to buyers, says Dragomir Golubović, Director of HDPE.
Stable production, with minor instrumental adjustments, has also been reached in the Low Density Polyethylene Plant. According to Đorđe Nadeždić, Director of LDPE, the maximum capacity has been reached for the polymer type 22003, which is currently being produced.
To remind, Ethylene plant has successfully started its production on Friday, April 27 ,and HDPE and Electrolysis have done the same on April 29, whereas during the Labour Day holiday besides minor difficulties, started its production LDPE.