Stoppage due to investments in HIP-Petrohemija
On August 1,In HIP-Petrohemija begins stoppage in production facilities operating, which will last until September 19,2015. This period will be used for carrying out investment projects in order to improve the energy efficiency of production and reduce production costs, as well as for the realization of overhaul activities.
"Stoppage of LDPE Plant because of the general overhaul of the compressor C-202 is scheduled from August 1. Stoppage in Ethylene Plant and other production facilities will begin on August 19, and will last until September 19. In addition to investment activities in Utility Plant, Ethylene Plant and HDPE Plant during the stoppage there will also be carried out overhaul activities on the process equipment in other plants, "- said Misha Bulajic, Executive Director of the functions of production and technical support in HIP Petrohemija and added:" All our customers have been informed on time about the goods deliveries during August and September, when we start again with the production."
Investment activities in Ethylene Plant and Utility Plant are focused on energy efficiency increasing,by which there will be achieved a reduction in natural gas consumption by 10% and improvement of our company operating. These projects are the first larger projects financed from the credit supported by the Government of Republic of Serbia.
The planned overhaul activities will ensure continuation of safe and efficient operating of the company and will be performed according to the predetermined plan. All working activities during the stoppage of production in HIP-Petrohemija are fully in line with the applicable security procedures of the company.