Tuesday, 18. December 2012.
HIP-Petrohemija visited by representatives of Ministry of Finance and Economy of Serbia and NIS
HIP-Petrohemija on Tuesday, 18 December, was visited by the Minister of the Finance and Economy of Serbia, Mlađan Dinkic. Accompanied by Director General of HIP- Petrohemija, Milan Teofilović and Director General of NIS, Kiril Kravčenko, the guests visited the plant for the production of high density polyethylene (HDPE), which reconstruction and increase of the capacity was in the first phase of the program of revitalization of the company, and which was carried out with logistical and consultation support of NIS and the Government of the Republic of Serbia.
Tuesday, 18. December 2012.
Modernized HDPE put into operation
Three days before the scheduled date for the start and four days after receiving a licence for probation on Tuesday, 18 December, HDPE plant 90kTA was put into operation and obtained the first quantity of polymer powder. Thanks to the modernization of HDPE, capacity was increased to 90 thousand tons per year with the possibility of reaching a capacity of 100 thousand tons.
Thursday, 06. December 2012.
HIP-Petrohemija Started Operating
By the start-up of Ethylene Plant, after several months of standstill, due to investment operations in HDPE Plant, production in HIP-Petrohemija started successfully.
Wednesday, 28. November 2012.
HDPE Reconstruction Soon Completed
“Investment operations on HDPE reconstruction are reaching their end and mechanical completion of the facility is expected on the first weekend of December, 1 and 2 December. By that time operations of contractor “Goša Montaža“, with whom we had great cooperation, will also be finished. The contractor will stay a bit longer in Petrohemija, due to possible repairs. After the mechanical mounting, instrumentation operations are 99 % done and electro operations are completely finished. Until the end of investment operations, it is necessary to perform corrosion protection and pipeline isolation, check sealings and wash all the systems.“ stated Vladimir Koprivšek, Executive Director for Production and Technical Operations and Manager of the Project Team.
Thursday, 08. November 2012.
The Second Month of HDPE Plant Reconstruction
The total realization of the project of the HDPE Plant reconstruction by 7 November has reached 73% regarding planned 76%. According to Vladimir Koprivšek, Executive Director for Productional and Technical Affairs and Project Manager of the Project Team, operations proceed very well thanks to great effort of main contractor “Goša Montaža“, performer of construction, electro and instrumental operations, as well as of employees of “Petrohemija“.
Thursday, 18. October 2012.
Ministry of Finance and Economy Representatives Visit
Monday, 08. October 2012.
The First Month of HDPE Plant Reconstruction
Saturday, 15. September 2012.
Dismantling completed and equipment installation started in HDPE Plant
For only twelve days since the investment operations officially started in HIP-Petrohemija, on September 15th, 2012, the PF section dismantling in the HDPE Plant was completed.
Saturday, 08. September 2012.
HDPE Plant reconstruction started
On Monday, September 3rd, 2012, the operations on HDPE Plant reconstruction officially started. During the last week in August the main contractor “Gosa montaza“ from Velika Plana completed all preliminary works for starting this reconstruction, so they began dismantling works in the plant on Monday, September 3rd, at noon time.
Wednesday, 29. August 2012.
Milan Teofilovic – new Director General
Supervisory Board of HIP-Petrohemija, on the session held on Wednesday, August 29, appointed Milan Teofilović, Bachelor of Laws, Director General of the Company. Teofilovic has been part of the Management of HIP-Petrohemija since September 2009, at the position of Special Advisor to the Director General of the Company.