MAIN CAPEX PROJECTS:
Reinstrumentation of the Ethylene Plant. The objective of this project is implementation of high-end process controlled systems that will enable full control of the reaction of pyrolytic cracking and optimization of energy consumption. First phase will be finalised within the overhaul in Spring 2019. Worth of the project is estimated around 3.5 million € and it will be implemented in full cooperation with respectable global companies. Second phase of the project includes replacement of turbine control systems. Worth of the second phase of the project is estimated around 4.5 million €.
New sections of processing and packing in HDPE Plant. The objective of this project is production capacity increase in HDPE Plant. Estimated value of the project is around 10 million €.
Boiler Economiser installation in SBR Plant. The objective of this project is more efficient energy usage.
Compressor Recounstruction in LDPE Plant. The objective of this project is operational efficiency improvement.